Mount Wellington Marine Boat Stack

By Q Construction

Profile
Mount Wellington Marine Boat Stack banner

Construction of boat stacking facility at Mount Wellington for the original owners RPM Property.

We were engaged following the abandonment of contract works by other parties. As the site was established by Q and as part of our ‘as built’ surveys the works previously completed works were found to be non-compliant. In conjunction with our subcontractors we were able to formulate a method of removing all pre-existing works that minimised the significant time/cost implication of this error by other parties.

The challenge

With the site located on a historic volcanic plateau and close proximity to the mean high-water mark there was extensive basalt and other volcanic material that required breaking along with very high water tables that all dictated a very detailed methodology with respect to constructing the foundations including hydro excavation, rock breaker. The site had also been used to place non engineered fill to fill between the peaks of basalt. Extremely deep foundations spanning full width of the site also determined specific sequencing of works so works could progress in a manner where access was maintained for ALL effected parties.

The steel frame supply was by a nominated contractor and Q Construction were charged with sourcing suitably qualified steel assembly crews ‘untangling’ the web of supply information left over by previous contractors.

Due to the very high loadings imposed by the equipment associated with the facility usage a robust process was implemented to find a workable solution for a floor slab that was founded on unsuitable subgrade and needed to be self supporting between the foundation beam spans. QCC engaged their preferred contractor for this form of slab and were able to formulate a slab design that met all the necessary requirements.

The details

  • Multi-Tier Dry Stack Boat Storage Facility
  • Reinforced concrete foundations
  • Galvanised steel frame
  • Design and Build floor slab
  • Associated stormwater/wastewater management devices
  • Dockside modifications including new ramp and concrete block gravity retaining wall

Professionals used in
Mount Wellington Marine Boat Stack

About the
Professional

THIS IS US: Q CONSTRUCTION

Our experience in the industry told us clients were looking for people they can trust. People who have pride in seeing a job done well and last, but not least – people they enjoyed working with.

We also figured that if we’re going put our sweat and hours into a project, we may as well enjoy it. The happier, healthier our crew – the better the end result, for everyone.

We call this “The Power of Q” and it’s so powerful, clients want to come back, again and again.

No us and them.

No matter how large or how small your project, we believe in total collaboration. Construction is one of the most complicated industries with so many moving parts, so there has to be teamwork and a good measure of ingenuity. We create solutions that work, bring innovation that saves money, and have a can-do attitude that gets the job done on time.

CONSTRUCTION 

INTERIORS 

MAINTENANCE 

COLDSTORES

At ArchiPro we recognise and acknowledge the existing, original and ancient connection Aboriginal and Torres Strait Islander peoples have to the lands and waterways across the Australian continent. We pay our respects to the elders past and present. We commit to working together to build a prosperous and inclusive Australia.