5 things to consider before building on a constrained site

featuring Mancini Made

© Peter Clarke

© Peter Clarke

Mancini Made logo

On a tightly constrained Albert Park site, Mancini Made took on a three-level commercial and residential development that demanded ingenuity at every turn. The result is a richly detailed building that brings contemporary architecture into conversation with its heritage streetscape.

Visit Website

Featured Professionals

Written by

  • Joanna Seton

Whether it's a narrow inner-city section, a property hemmed in by neighbouring buildings or a site with heritage overlays, the challenges of building on a constrained site extend well beyond the design itself. Access, construction methodology, protection works and council requirements can all have a significant bearing on how a project unfolds, influencing everything from the programme to the final cost.

Having delivered more than 50 projects involving complex site conditions and heritage requirements, award-winning builders Mancini Made have developed a clear understanding of where the potential pitfalls lie. Directors Anthony and Paul Mancini say the key is to recognise the constraints early and assemble a team with the experience to work through them.

Here, they share five things worth considering before embarking on a challenging build on a constrained site.

1. Get your architect and builder involved from the outset

One of the biggest mistakes clients can make is treating the design and construction phases as entirely separate processes. On a constrained site, decisions made during the initial design can have significant implications for how a building is actually constructed.

Access for materials and equipment, the ability to work along boundary walls, protection requirements and the choice of construction system all need to be considered before plans are submitted for consent. Once documentation has gone through the planning process, making substantial changes can be difficult and expensive.

Anthony recommends bringing an experienced builder into the conversation early, allowing the design team to test its ideas against the practical realities of construction.

“The best outcomes are when the client, architect and builder work together from the outset,” he says. “That can save a lot of time and money.”

For projects involving heritage restrictions, he also recommends engaging an architect with a proven track record in this area, ideally someone who has worked with the relevant local council before. A heritage consultant can provide further guidance on what is likely to receive approval before significant time and money are invested in a design.

© Timothy Kaye

© Timothy Kaye

2. Think carefully about your boundary materials

The choice of external materials can make an enormous difference to the complexity of building on a tight site. This is particularly relevant when construction or finishing work needs to be carried out along a boundary where there is little or no room for scaffolding.

Paul points to the Victoria project in Albert Park, Melbourne as an example. The three-level commercial and residential development required work along both side boundaries, including rendering masonry walls. This meant the team needed access for scaffolding, which became a particularly difficult issue given the neighbouring properties and their protection requirements.

His advice to architects is to consider whether a prefabricated or prefinished material could achieve the same result with considerably less on-site work.

Tilt panels, for example, or other prefinished wall systems can be installed without requiring extensive finishing work at the boundary. While the initial material cost might be higher, the reduction in scaffolding, labour and potential delays could make it a more economical solution overall.

“From a design viewpoint, if you're working in tight spaces, take consideration of any prefinished material on the boundary,” Paul says. “It would be better than having to render it.”

3. Understand neighbouring-property and protection requirements

On a tightly bound site, neighbouring properties can have a surprisingly significant influence on the construction programme. Protection works may be required to safeguard adjoining buildings during excavation and construction, while scaffolding, access and other temporary works can require formal agreements with neighbouring owners.

Anthony says these arrangements can be unpredictable. Negotiations can take lengthy periods, which can set the building timeline back significantly. 

For clients, the important thing is to understand these requirements before construction begins, including who is responsible for obtaining agreements, what access may be needed and how potential delays or costs will be managed.

For builders, Anthony has a more specific recommendation: exclude protection works negotiations and their outcomes from the building contract wherever possible.

“Negotations could take two weeks, they could have 10 weeks, or the neighbours could ask for $100,000. Sometimes it's for free,” he says.

It's a reminder that even with excellent planning, some aspects of a constrained-site build sit outside the builder's control. Making responsibilities clear from the beginning helps protect the project programme and the businesses involved.

© Peter Clarke

4. Treat heritage as a specialist discipline

Working with an existing heritage building requires considerably more care than simply retaining a façade or repairing a few architectural details. There may be strict requirements around what can be removed, how original materials are handled and whether existing elements can be reused.

Paul recommends commissioning a comprehensive dilapidation report before work begins, supported by detailed photography and documentation. Any materials that need to be 

dismantled should be carefully stored and made available for council inspection where required.

The level of detail can be surprisingly exacting. On another Mancini Made project, the team was required to number individual bricks as a chimney was dismantled, allowing the original masonry to be documented, inspected and potentially reinstated.

“It's not just pulling things down and putting them to one side,” Paul says. “You need to understand what that material is. Can we replace it? Is it good enough? Can it go back up?”

He also emphasises the value of maintaining an open and collaborative relationship with council throughout the process. An experienced heritage builder will understand the documentation, sequencing and communication required to keep the work moving.

5. Choose your team on experience, not just price

When a project involves multiple constraints, the experience of the people delivering it becomes particularly important. A builder who understands complex access arrangements, protection works and heritage documentation is better equipped to anticipate problems and find workable solutions.

Anthony recommends looking beyond a builder's portfolio of finished projects. Ask to visit completed sites, speak directly with previous clients and establish how much relevant experience the company actually has.

Mancini Made has completed more than 50 projects involving these kinds of challenges, and Anthony says the level of documentation and planning required can be substantial. Detailed photography, records of existing conditions and careful management of approvals are all part of protecting the client, the builder and the building itself.

The same scrutiny should apply to the architect. Someone familiar with the local planning environment and experienced in designing for constrained sites can help avoid costly decisions further down the track.

Ultimately, Anthony says, the goal is to eliminate as much uncertainty as possible before construction starts.

“It's all about mitigating risk. You want to streamline the process and make the whole programme as seamless as possible,” he says.

With construction costs continuing to put pressure on project budgets, investing in the right expertise at the beginning can be far more valuable than saving a little on professional fees. A constrained site will always demand more thought, but with the right people around the table, many of its challenges can be anticipated and resolved before they become problems on site.